| Port Westward Generating Project |
|
|
 |
|
|
Facility: 650 MW natural gas combined-cycle combustion turbine system
Location: Columbia County
Status:
Operating since July 19, 2007.
Certificate Holder: Portland General Electric Company
Contact:
Arya Behbehani-Divers
Portland General Electric Company
121 SW Salmon Street
Portland OR 97204
503-464-8141
Department of Energy staff: Duane Kilsdonk
Original site certificate signed: November 12, 2002
Current site certificate: Seventh Amended Site Certificate (pending)
History:
- February 27, 2001: Notice of intent submitted.
- April 28, 2001: Department of Energy issued a project order.
- August 16, 2001: Application submitted.
- November 5, 2001: Department of Energy issued an amended project order.
- April 11, 2002: Application complete (date of filing).
- June 26, 2002: Department of Energy issued a draft proposed order.
- August 1, 2002: Public hearing held in Clatskanie, Oregon.
- August 23, 2002: Department of Energy issued a proposed order.
- August 26, 2002: Contested Case Notice.
- November 8, 2002: Council approved a site certificate.
- September 25, 2003: Request for Amendment #1 received.
- December 5, 2003: Council approved Amendment #1.
- May 7, 2004: Request for Amendment #2 received.
- August 10, 2004: Department issued a proposed order on Amendment #2.
- September 24, 2004: Council approved Amendment #2.
- December 16, 2004: Department issued a proposed order on Amendment #3.
- January 28, 2005: Council approved Amendment #3.
- February 14, 2005: Construction begun.
- January 17, 2006: Request for Amendment #4 received.
- February 6, 2006: Department issued a proposed order on Amendment #4.
- February 10, 2006: Council approved Amendment #4.
- May 19, 2006: Council issued a final order on Amendment #4.
- July 20, 2006: Request for Amendment #5 received.
- August 22, 2006: Department issued a proposed order on Amendment #5.
- September 20, 2006: Council approved Amendment #5.
- November 7, 2008: Request for Amendment #6 received.
- February 23, 2009: Department issued a proposed order on Amendment #6.
- March 27, 2009: Council approved Amendment #6.
- September 18, 2009: Request for Amendment #7 received.
- January 13, 2010: Department issued a proposed order on Amendment #7.
- March 12, 2010: The Council approved Amendment #7.
- November 4, 2010: Request for Amendement #8 received.
- January 5, 2011: Department issued a Draft Proposed Order on Amendment #8.
- June 9, 2011: Department issued a Proposed Order on Amendment #8
Documents:
- Site Certificate, November 2002
- Final Order on Amendment #1, December 2003
- First Amended Site Certificate, December 2003
- Final Order on Amendment #2, September 2004
- Second Amended Site Certificate, September 2004
- Final Order on Amendment #3, January 2005
- Third Amended Site Certificate, January 2005
Attachment A: Monetary Path Payment Requirement Attachment A1: Monetary Path Payment Requirement with Standby Letter of Credit Attachment B-1: Proposed Water Pollution Control Facilities Permit Attachment B-2: Onsite WPCF Permit Evaluation Attachment C-1: Proposed Removal/Fill Permit Attachment C-2: Special Conditions for Removal/Fill Permit
- Temporary Order on Amendment #4, February 2006 [71 kb pdf]
- Final Order on Amendment #4, May 2006 [113 kb pdf]
- Fourth Amended Site Certificate, May 2006 [260 kb pdf]
- Request for Amendment #5, July 2006 [78 kb pdf]
Figure 1 [684 kb pdf] Figure 2 [386 kb pdf]
- Final Order on Amendment #5, September 2006 [60 kb pdf]
- Fifth Amended Site Certificate, September 2006 [168 kb pdf]
- Request for Amendment #6, November 2008 [231 kb pdf]
- Sixth Amended Site Certificate, March 2009[210 kb pdf]
- Proposed order on Amendment #7, January 2010 [321 kb pdf]
- Final Order on Amendment 7 [777 kb pdf]
- Request for Amendment #8, November 4, 2010
- Draft Proposed Order on Amendment #8, January 2011 [295 kb PDF]
- Proposed Order on Amendment #8, January 2011 [466 kb PDF]
|
|
| |
|
|