Text Size:   A+ A- A   •   Text Only
Oregon Department of Energy logo
Leaning Juniper II Wind Power Facility
Facility:
A wind energy facility with a peak generating capacity of approximately 201 megawatts.
 
Location: Gilliam County
 
Status:

The facility is operating.
 
Certificate Holder:
Leaning Juniper Wind Power II, LLC
 
Contact:
Sara Parsons
Leaning Juniper Wind Power Facility
c/o Iberdrola Renewables, Inc.
1125 NW Couch St., Suite 700
Portland, OR 97209
 
(503) 796-7732
 
Department of Energy Staff: John White
 
Original site certificate signed: September 24, 2007
 
Current site certificate: First Amended Site Certificate (November 24, 2009)
 
History:
  • November 30, 2005: Applicant submitted a request for expedited review.
  • December 15, 2005: Department of Energy approved expedited review.
  • February 1, 2006: Preliminary application submitted.
  • October 4, 2006: Amended preliminary application submitted.
  • May 15, 2007: Application filed (complete).
  • July 18, 2007: Department of Energy issued a Draft Proposed Order.
  • August 9, 2007: Public hearing on Draft Proposed Order.
  • August 21, 2007: Department of Energy issued a Proposed Order.
  • September 21, 2007: Council approved a site certificate 
  • September 24, 2007: Site Certificate became effective.
  • June 19, 2009: Certificate holder submitted a Request for Amendment #1.
  • October 15, 2009: Department of Energy issued a Proposed Order on Amendment #1.
  • November 20, 2009: Council approved Amendment #1.
  • November 24, 2009: First Amended Site Certificate became effective.
  • February 15, 2010: Beginning of construction (LJIIA).
  • March 16, 2010: Beginning of construction (LJIIB).
  • June 9, 2011: Beginning of operation. 
 
Documents: